Project Brief


Site Introduction

Metropolitan Police - Fresh Wharf Patrol Base. 

Scope of Works

Hollmark were employed by McDonald Brown via Willmott Dixon, to supply and install fire compartmentation partition walls. The system we installed was a British Gypsum (A206013 (EN)) single frame, which gives a 97mm thick wall and provides a 30 minute fire performance. We formed openings for service penetrations running through our partition wall, ensuring that the fire integrity was not compromised. 

ON Site CHALLENGES

The Police base was a live site and therefore this made the logistics of working there complex. Special consideration, in particular, had to be made to the adherence of security protocols. A detailed programme of works and strategy was produced, ensuring materials were delivered safely and in a timely manner to site, and operatives were in agreed working areas at the appropriate times.

SPECIFIC SKILLSET IN PROJECT

Hollmark used this project to be successfully audited by our third party accreditors, the LPCB (Loss Prevention Certification Board).



CLIENT

Willmott Dixon on behalf of McDonald Brown

PROJECT DURATION

November 2021 to February 2022

PROJECT VALUE

£32,000.00

To find out more about Hollmark passive fire protection services, contact us on 01277 626101
or email us at
info@hollmarkfireprotection.co.uk

Our Accreditations

Thanks to our innovative approach, we’ve received accreditation from these leading industry bodies.


Share by: